I haven’t had any experience in the past with working with Construction Managers, so I feel like I really had to go the extra mile to understand all the differences and roles & responsibilities in the different CM project delivery methods. I’ve created some very handy charts to help explain the differences between CMa and CMc, I may release it later when I’m less overwhelmed.
I’m also trying to get back into the habit of regular note taking instead of being so focused on watching the explanatory videos. I was really inspired by this video I watched today by Jorge Herrera on quick study tips. I’ll probably be buying an assortment of notebooks and binders for my path forward, and take advantage of some of these back to school sales.
Question 01
Joanne Bowman is the manager of a government branch looking to expand in the near future. She is looking for a high-quality design, with low risk. Which project delivery methods would you, as her architect, recommend to her? (Select two)
- Design-Bid-Build
- Construction Manager as Advisor
- Construction Manager as Constructor
- Integrated Project Delivery
Question 02
While on the construction site, the Project Architect Maryam Lanoir notices a defect in the work. Since this project is a Construction Manager as Advisor project delivery method, what should be her next steps?
- Instruct the superintendent to correct the deficiency, as per the contract drawings
- Notify the Owner
- Notify the Contractor
- Notify the Construction manager
- All of the above
Question 03
Jessica Trevi is an architect providing construction administration services on a Construction Manager as Advisor project. What is not a joint service that she provides?
- Certifying applications for payment
- Preparing change orders
- Reviewing RFIs
- Rejecting work

Question 01
CORRECT ANSWERS
- Construction Manager as Constructor
- Integrated Project Delivery
Both CMc and IPD are preferred in projects with high building quality standards, and where owners want to reduce their risk.
inCORRECT ANSWERS
Construction Manager as Adviser is a preferred choice for reducing project risk, but it is not always used for high building quality. Design-bid-build, is known for being low cost, which also can create low quality, as well as being high risk.
For reference, read Ballast Chapter 3.
Question 02
While on the construction site, the Project Architect Maryam Lanoir notices a defect in the work. Since this project is a Construction Manager as Advisor project delivery method, what should be her next steps?
- Notify the Owner
- Notify the Contractor
- Notify the Construction Manager
With CMa projects, it is the architect’s responsibility to notify the Owner and the Construction Manager of any observed defects and deficiencies. See A232 – Article 4.2.2
The architect is not able to issue instructions to the superintendent. According to A232 – Article 3.9.1, it is only communications, not instructions that can be given to the superintendent.
Question 03
Jessica Trevi is an architect providing construction administration services on a Construction Manager as Advisor project. What is not a joint service that she provides?
Preparing change orders
CORRECT ANSWER
Preparing change orders or construction change directives is not a joint service provided the architect in construction administration.
Certifying applications for payment, RFI review and rejecting work is something that is done by both the CM and architect in a CMa project delivery.
I hope you like this mini quiz. Let me know how you did in the comments, or on the RMSM Studio Facebook page.
All of my recent practice questions are now available in one place, on the Practice Questions page in the top menu.
If you want to find other great practice tests, you can also have a look at my One Minute Reviews, where I give my feedback on ARE study materials in under a minute.