Mini Quiz: CM Project Delivery Methods

Mini Quiz from RMSM Studio on Construction Manager Project Delivery Methods

I haven’t had any experience in the past with working with Construction Managers, so I feel like I really had to go the extra mile to understand all the differences and roles & responsibilities in the different CM project delivery methods. I’ve created some very handy charts to help explain the differences between CMa and CMc, I may release it later when I’m less overwhelmed.

I’m also trying to get back into the habit of regular note taking instead of being so focused on watching the explanatory videos. I was really inspired by this video I watched today by Jorge Herrera on quick study tips. I’ll probably be buying an assortment of notebooks and binders for my path forward, and take advantage of some of these back to school sales.

Question 01

Joanne Bowman is the manager of a government branch looking to expand in the near future. She is looking for a high-quality design, with low risk. Which project delivery methods would you, as her architect, recommend to her? (Select two)

  • Design-Bid-Build
  • Construction Manager as Advisor
  • Construction Manager as Constructor
  • Integrated Project Delivery

Question 02

While on the construction site, the Project Architect Maryam Lanoir notices a defect in the work. Since this project is a Construction Manager as Advisor project delivery method, what should be her next steps?

  • Instruct the superintendent to correct the deficiency, as per the contract drawings
  • Notify the Owner
  • Notify the Contractor
  • Notify the Construction manager
  • All of the above

Question 03

Jessica Trevi is an architect providing construction administration services on a Construction Manager as Advisor project. What is not a joint service that she provides?

  • Certifying applications for payment
  • Preparing change orders
  • Reviewing RFIs
  • Rejecting work

Question 01

CORRECT ANSWERS

  • Construction Manager as Constructor
  • Integrated Project Delivery

Both CMc and IPD are preferred in projects with high building quality standards, and where owners want to reduce their risk.

inCORRECT ANSWERS

Construction Manager as Adviser is a preferred choice for reducing project risk, but it is not always used for high building quality. Design-bid-build, is known for being low cost, which also can create low quality, as well as being high risk.

For reference, read Ballast Chapter 3.

Question 02

While on the construction site, the Project Architect Maryam Lanoir notices a defect in the work. Since this project is a Construction Manager as Advisor project delivery method, what should be her next steps?

  • Notify the Owner
  • Notify the Contractor
  • Notify the Construction Manager

With CMa projects, it is the architect’s responsibility to notify the Owner and the Construction Manager of any observed defects and deficiencies. See A232 – Article 4.2.2

The architect is not able to issue instructions to the superintendent. According to A232 – Article 3.9.1, it is only communications, not instructions that can be given to the superintendent.

Question 03

Jessica Trevi is an architect providing construction administration services on a Construction Manager as Advisor project. What is not a joint service that she provides?

Preparing change orders

CORRECT ANSWER

Preparing change orders or construction change directives is not a joint service provided the architect in construction administration.

Certifying applications for payment, RFI review and rejecting work is something that is done by both the CM and architect in a CMa project delivery.


I hope you like this mini quiz. Let me know how you did in the comments, or on the RMSM Studio Facebook page.

All of my recent practice questions are now available in one place, on the Practice Questions page in the top menu.

If you want to find other great practice tests, you can also have a look at my One Minute Reviews, where I give my feedback on ARE study materials in under a minute.

Mini Quiz: Risk Management

Mini Quiz from RMSM Studio on the Management of Risk For Architects

Risk Management is one of the key concepts in all stages of design. This is because whenever you are creating a building, you must always assume some risk. This is an essential concept for both Practice Management and Project Management. In the Wiley AHPP Guide for the Project Management (PjM) Exam, under the Risk Management chapter, they just say “All”. It’s that important. I hope you enjoy this mini quiz and as always, let me know how you did in the comments.

Question 01

Which types of firms will some underwriters have hesitation insuring?

  • Those with low deductibles
  • Those that don’t provide construction administration services
  • Those with a high number of inexperienced employees
  • Those using the AIA contract document suite

Question 02

Jay York, Esq. is an attorney who has been hired by Jasmine Board Architects. They have been hired to review their proposed insurance policies. Which of the following policy’s should Jay mark for further review with Jasmine Board Architects?

  • Indemnification for those not party to the Agreement
  • Client indemnity to architect for misuse of the architect’s drawings
  • Defending the Owner against third-party claims
  • Mutual indemnities between architects and consultants
  • All of the above

Question 03

Select all problematic words from the advertisement below created by Diedre Lock Associates:


Question 01

Those that don’t provide construction administration services

There is a high number of claims that arise when an architect only provides pre-construction services, as they are not there to defend themselves or their drawings.

Incorrect Answers

  • Those with low deductibles – Deductibles with another insurer would not affect another company’s coverage.
  • Those with a high number of inexperienced employees – As long as there are staff available that are qualified to complete the projects on hand, the number of inexperienced employees is irrelevant.
  • Those using the AIA contract document suite – Using a the standard AIA contract documents means that an insurer specializing in construction would be more likely to insure you, due to the industry’s familiarity with them.

Question 02

Policies that should be reviewed, due to being unmanageable risks, are:

  • Indemnification for those not party to the Agreement
  • Client indemnity to architect for misuse of the architect’s drawings
  • Defending the Owner against third-party claims

Incorrect Answers

Mutual indemnities between architects and consultants is actually a beneficial policy for an architect’s agreement. Study B101 8.4 for a good model of policies.

Question 03

The problematic words in this advertisement were:

  • Ensure
  • Best
  • 100% Completion
  • All
  • Assured
  • Thorough
  • Best
  • Guaranteed

I hope you like this mini quiz. Let me know how you did in the comments, or on the RMSM Studio Facebook page.

If you’re studying for Practice Management, feel free to check out my other Mini Quiz on the AIA A201 Document and my post on passing the PcM Exam. I have also created a one-page study guide based on the methods I used to pass PcM on the first try.

If you’re studying for Construction & Evaluation or Project Management, check out my Mini Quiz on the AIA C401 Contract.

All of my recent practice questions are also available for you to scroll through below, or on the specific page I’ve created for them at the top of the website:

If you want to find other great practice tests, you can also have a look at my One Minute Reviews, where I give my feedback on ARE study materials in under a minute.

Mini Quiz: Project Management

Mini Quiz from RMSM Studio on the Project Planning and Management

I’ve created these questions based on the Ballast Review Manual, which you can find for on Amazon, or search for a used version in the ARE Facebook Group. The Ballast Review Manual comes very highly recommended for multiple ARE exams, and you can check out the Young Architect website for a 15% off discount from PPI2Pass.

Question 01

Within the Critical Path Method (CPM), which items are denoted by a solid arrow?

  • Dummies
  • Tasks
  • The Critical Path
  • Dependencies

Question 02

Which elements form part of the project work plan? (Select all that apply)

  • Allocation of time and fees
  • Staff Required
  • Instruments of service
  • Milestones
  • Contingencies
  • Consultant work and fees

Question 03

Architects should consider the follow issues when assembling a project team, except for: (Select one)

  • Billing Rates
  • Project Size and Complexity
  • Personalities
  • Contractor Experience

Question 04

What is the typical fee percentage for Design Development?

  • 15%
  • 20%
  • 30%
  • 40%

Question 01

Within the Critical Path Method (CPM), which items are denoted by a solid arrow?

  • Tasks

Dummies are represented by dashed arrows, as opposed to the heavy dashed arrows which show the Critical Path. Dummies are another name for Dependencies.

Ballast, page 4-6

Question 02

Which elements form part of the project work plan? (Select all that apply)

  • Allocation of time and fees
  • Staff Required
  • Milestones
  • Consultant work and fees

Though the project can be broken down into phases and individual tasks, the instruments of service themselves are not an element of the project work plan.

Although time and fees allocated to the project can both include contingencies, contingencies themselves are not an element of the project work plan.

Ballast, page 4-8

Question 03

Architects should consider the follow issues when assembling a project team, except for: (Select one)

  • Contractor Experience

Architects do not make the selection for contractors, though contractors can be a part of the overall project team.

Ballast, page 4-4

Question 04

What is the typical fee percentage for Design Development?

  • 20%

On a typical design-bid-build project, the fee percentages are as follows:

Schematic Design: 15%

Design Development: 20%

Construction Documentation: 40%

Bidding: 5%

Contract Administration: 20%

Ballast, page 4-9


I hope you like this mini quiz. Let me know how you did in the comments, or on the RMSM Studio Facebook page. If you got none of them right, it’s time to hit the books!

If you’re studying for Project Management, feel free to check out my other Mini Quiz on the A201, and if you’re studying for Construction & Evaluation, check out my Mini Quiz on C401.

If you want to find other great practice tests, you can also have a look at my One Minute Reviews, where I give my feedback on ARE study materials in under a minute.

Mini Quiz: AIA Code of Ethics and Professional Conduct

Mini Quiz from RMSM Studio on the AIA Code of Ethics and Professional COnduct 2018

I’ve created these questions based on the 2018 AIA Code of Ethics and Professional Conduct, which you can find for free here. This is a very short, easy to read document, but very important to professional practice.

Question 01

Which Ethical Standards fall under Canon VI: Obligations to the Environment?

  • Alternative energy sources
  • Building materials
  • Indoor Air Quality
  • None of the Above

Question 02

Penalties imposed by the National Ethics Council include: (Select all that apply)

  • Censure, with appeal
  • Admonition, with appeal
  • Litigation, with appeal
  • Suspension of membership, with appeal
  • Termination of membership, without appeal

Question 03

An architect wants to file a claim against another architect using Rule 4.101 of the Code of Ethics. What actions must they take?

  • Consult their legal counsel
  • Ensure proof of violation of one other rule
  • Consult their insurance company
  • Ensure proof of fraud based on an independent finding of a violation of the law

Question 04

What Canon does this statement fall within:

Members shall continually seek to raise the standards of aesthetic excellence, architectural education, research, training, and practice.

  • Canon II: Obligations to the Public
  • Canon I: General Obligations
  • Canon V: Obligations to Colleagues
  • Canon IV: Obligations to the Profession

Question 01

Which Ethical Standard fall under Canon VI: Obligations to the Environment?

  • Building materials

All other answers are not ethical standards under Canon VI: Obligations to the Environment.

Question 02

Penalties imposed by the National Ethics Council include: (Select all that apply)

  • Censure, with appeal
  • Admonition, with appeal
  • Suspension of membership, with appeal

Litigation is not a penalty imposed by the Natinoal Ethics Council. All penalties allow for appeal procedures, so “Termination of membership, without appeal” is incorrect.

Question 03

An architect wants to file a claim against another architect using Rule 4.101 of the Code of Ethics. What actions must they take?

  • Ensure proof of violation of one other rule

Under Canon IV: Obligations to the Profession: “Enforcement of Rule 4.101 refers to and supports enforcement of other Rules. A violation of Rule 4.101 cannot be established without proof of a pertinent violation of at least one other Rule.”

Question 04

What Canon does this statement fall within:

Members shall continually seek to raise the standards of aesthetic excellence, architectural education, research, training, and practice.

  • Canon I: General Obligations

I hope you like this mini quiz. Let me know how you did in the comments, or on the RMSM Studio Facebook page. If you’re studying for Practice Management, feel free to check out my other Mini Quiz on the A201 and my post on passing the PcM Exam, and if you’re studying for Construction & Evaluation, check out my Mini Quiz on C401.