Mini Quiz: A201

A 4 question quiz on the General Conditions of the Contract for Construction. The answers are provided after the questions. The A201 contract is available as a free download from the AIA website, and I’m currently studying it in preparation for my upcoming Project Management (PjM) and Construction & Evaluation (CE) Exam. It is listed within the ARE 5.0 Reference Matrix as a study material for PjM. Good luck studying, and if you have any questions, let me know in the comments!

Question 01

When does the Owner not have to share information about their financial arrangements for the Work?

  • Prior to the commencement of the work
  • When the Owner fails to make payments as per the contract documents
  • When a change in the work materially changes the contract sum
  • When the Architect issues a Certificate for Payment

Question 02

A Modification is all of the following, except for a: (Choose 1)

  • Construction Change Directive
  • Written Order for a minor change in work issued by the Owner
  • Change Order
  • Written Amendment to the Contract signed by both parties

Question 03

The Contractor shall immediately suspend any operations if they encounter the following conditions, except for:

(Choose 1)

  • Wetlands
  • Archaeological Sites
  • Burial Markers
  • Contract Documents in violation of applicable laws

Question 04

Select all items provided and paid for by the Contractor:

  • Sales Tax
  • Approvals for Occupancy
  • Temporary facilities not incorporated in the work
  • Utilities
  • Equipment and Machinery
  • Transportation

Question 01

When does the Owner not have to share information about their financial arrangements for the Work?

Correct Answers

  • When the Architect issues a Certificate for Payment

Incorrect Answers

Prior to the commencement of the work – Article 2.2.1 Prior to commencement of work and upon written request of the contractor, the owner shall furnish to the contractor evidence that the owner has made financial arrangements

When the Owner fails to make payments as per the contract documents & When a change in the work materially changes the contract sum – See Article 2.2.2

Question 02

A Modification is all of the following, except for a: (Choose 1)

Correct Answer

  • Written Order for a minor change in work issued by the Owner – Owners do not issue minor changes in work, those are issue by the Architect

Incorrect Answers

Construction Change Directive, Change Order, and a Written Amendment to the Contract signed by both parties: are all listed under Article 1.1.1 as Modifications.

Question 03

The Contractor shall immediately suspend any operations if they encounter the following conditions, except for:

Correct Answer

  • contract documents in violation of applicable laws – Article 3.2.3 The Contractor is not required to suspend work upon discovery of a nonconformity of the Contract Documents, only required to promptly report to the Architect

Incorrect Answers

According to Article 3.7.5 if the COntractor discovers any of these conditions, they shall immediately suspend operations:

  • Wetlands
  • Archaeological sites
  • Burial markers

Question 04

Select all items provided and paid for by the Contractor:

Correct Answer

  • Sales Tax – Article 3.6 Taxes
  • Temporary facilities not incorporated in the work – Article 3.4.1
  • Utilities – Article 3.4.1
  • Equipment and Machinery – Article 3.4.1
  • Transportation – Article 3.4.1

Incorrect Answers

All other items are to be provided by the Contractor.

  • Approvals for Occupancy – Provided by the owner as per Article 2.3.1

Thanks for taking part in my quiz, let me know how you did in the comments! You can also check out my mini quiz for C401 or check out my reviews for other practice exam providers.

#ARE100Challenge Day 1: Starting My Challenge

Thank you to everyone who expressed interest and support in this challenge within the ARE test taking community, especially within the ARE Facebook Group. After introducing the challenge, I thought it would be a good idea to share my own journey with using it.

My initial plan was to start the #ARE100Challenge the same day that I released it, but I decided to push it back for a few reasons:

  1. My tests, like many others, were rescheduled. As soon as the notice from NCARB regarding the cancellations, I decided, with COVID-19, that I didn’t want the additional stress of an uncertain test date on top of everything else. So my next test is scheduled for July.
  2. I have difficulty retaining information from too far back in the past. Even if I started studying now, I’m sure that I would end up forgetting a lot of the concepts I learned back in April.
  3. I wanted to take a break to reassess my priorities and get in the right mindset for studying. Rescheduling my exams took a lot of motivation out of me, and my head wasn’t in the right space.

So I am starting my countdown timer from the first day: You can find the link to my #ARE100Challenge Countdown from Day 60 here.

#ARE100Challenge Graphic. Created by RMSM Studio.

ARE 100 Challenge Countdown: 60 Days Left

HOUR COUNT: 0 OF 100 HOURS

Studying for: construction & Evaluation (CE)

challenge step: step 1. Read All required Textbooks first!

My goal for today and the next few weeks is to read as many of the main textbooks for my exam. This includes the AHPP, Ballast, and some of the Kaplan books which I’ve been able to purchase to give me a general understanding of the Construction Administration topics.

I’ve already completed the Wiley/Namour Wright Guide for the Architect’s Handbook of Professional Practice. However, tied into the concept of me losing things if I haven’t studied them recently, I would prefer to read them as second time as the last resource within this Challenge Step.

I feel like one thing this challenge allows me to do is be focused on one material at a time, instead of trying to jump from reference to reference. Cross training with different mediums is important, from audio lectures, to videos and practice exams. However, I believe cross training will come more into play once I have learned the essential concepts for this exam.

I will mainly be using the Clockify website to track my hours for this challenge, as it is a really easy interface for me to use. I’ve described how I used it to pass PcM here, along with other digital tools. I also plan on sharing a live webinar this month, on using Clockify to study more effectively for the ARE exam, so keep an eye out for that announcement.

Want to Participate in the #ARE100Challenge?

Download the Challenge Rules, and share your progress on social media using the #ARE100Challenge hashtag. Share your study materials, tips, diagrams, breakthroughs, frustrations, and successes on Facebook, Instagram or Twitter.

Record your progress and study hours daily or weekly it’s up to you!